Project spec was to remove internal walls, create new internal door opening, brick and block up widow and door as per plans supplied by architect. 

Temporary screens were installed to keep dust downstairs as clients had move upstairs whitest the work was carried out. 

Floor joists were propped up and walls carefully removed. Steel beams were fitted as per plans. Acro props removed and steel beams checked by the local building control.

We removed the garage ceiling and installed new insulation and plasterboard.  External wall in the garage was insulated and plaster boarded.

External door and window was removed and brick arch.  We then brick and blocked up the opening.  The brick match was not an issue as the clients will be painting the external brickwork.

We also removed the downstairs ceilings, insulated and fitted new plasterboard ceiling. 

The project was left ready for the other trades to continue which was being organised by the client.